Progress of the WTS-hall

September 2021 - Laage

Location Laage Hans Adam Allee

The WTS hall is taking shape!
As things stand, the roof sealing work for the production hall has already been completed and the floor laid. That means for us: Moving into the hall is planned from December, starting with the transfer of the first welding systems.
At the same time, the construction of the office building will continue and the outdoor facilities, parking spaces, access roads and concreting of the foundation for the gas tanks will be carried out.
Office building: At present, only the shell is in place; occupation is planned for the end of the complete construction work.
The planned completion of the construction project - according to the current schedule - is the end of March 2022!

Photo: © Jörn Lehmann – www.lehmann-photo.de